Performance of Auvere Power Plant

The objective of the overview is to identify the costs incurred after the acceptance of the Auvere Power Plant, the scheduled and extraordinary stoppages, the lessons learnt and the future plans of the power plant.

Area of government Ministry of the Environment, Ministry of Finance
Institution to be audited
Auditees
Audit Department Analysis Department
Director of Audit Märt Loite
Audit Team Märt Loite, Dmitri Teras
Contacts
Audit Number 80150

Remarks

Planned Start 1st half of 2024 Actual Start 1st half of 2024
Planned End 1st half of 2024 Actual End
Status Work in progress
Related Audits
Created on 12/22/2023
Last modified on 5/10/2024